One of the first questions we get from owners in Torre del Mar, Nerja or the villages is: "Do I actually need a licence for this?" The honest answer, for almost any building work in Spain, is yes — but the type of licence, the cost and the paperwork vary enormously. This guide explains the two categories in plain English, based on how the town halls in the Axarquia actually handle them.
The two types of licence
Spanish municipalities divide building work into two categories:
- Licencia de obra menor — "minor works". Anything that does not touch the structure, the building's footprint, its volume or its external appearance in a significant way. Think bathroom and kitchen refits, retiling, replacing windows like-for-like, plastering and painting, internal non-structural changes, repairs to terraces and roofs.
- Licencia de obra mayor — "major works". Anything structural or that changes the building: extensions, removing load-bearing walls, new floors or roofs, changes of use, new swimming pools, and most work on protected or rural properties. An obra mayor needs a project signed by an architect and usually an aparejador (technical architect) to supervise it.
In practice, many town halls in the Axarquia (Vélez-Málaga included) now run a fast-track system for the simplest minor works called a declaración responsable — a signed declaration that the work complies, which lets you start immediately rather than waiting for a licence to be issued. Your builder or gestor should know which route your town hall uses.
What does a licence cost?
Two charges apply: a tasa (administrative fee, usually small) and the ICIO — a construction tax charged as a percentage of the declared cost of the works, typically around 3–4% in this area. So on a €6,000 bathroom refit, expect roughly €200–€300 in licence costs. For an obra mayor, add the architect's project fees, which for a modest extension start at a few thousand euros and depend on the size and complexity of the job.
How long does it take?
A declaración responsable is effectively immediate. A standard licencia de obra menor in Vélez-Málaga, Nerja or Torrox can take anywhere from a couple of weeks to two months depending on how busy the department is. An obra mayor is a different animal: three to six months is normal, sometimes longer if the property is in a protected old-town area or on rural land. Plan around it — nobody wants an architect's project sitting on a desk while the summer rental season passes.
Apartments: your comunidad has a say too
If you own a flat, the town hall is only half the story. The comunidad de propietarios must be informed of any works, and anything that affects the façade, terraces, shared pipework or the structure needs the community's approval at a meeting. Working hours are also usually restricted by the community rules — typically no noisy work at siesta time or on Sundays. A good builder will handle the notification for you and keep the neighbours on side.
What happens if you skip it?
People do, and it usually goes fine — until it doesn't. The risks are real: a fine, a stop order half-way through the job, problems when you come to sell (the buyer's lawyer will ask), and difficulty legalising the work later. On rural land the consequences of unlicensed building can be far more serious. For the few hundred euros a minor-works licence costs, it is simply not worth it.
Rural land is different
Country properties around Viñuela, Frigiliana and the Torrox campo sit on suelo rústico, where new built area is tightly controlled. Repairs, maintenance, pergolas and some conversions of existing space are often possible; new extensions frequently are not. We tell every campo client at the first visit what is realistic — before anyone falls in love with a plan.
How we handle licences for you
For every quote we give, we state which licence the job needs. For obra menor work we prepare and submit the paperwork on your behalf, including the budget breakdown the town hall asks for. For obra mayor projects we introduce you to local architects we work with regularly, and we coordinate the project with them so the build and the paperwork move together. No surprises half-way through.
Planning a reform, extension or renovation in the Axarquia? Ask us for a free written quote — we will tell you exactly what permissions it needs.